- by Mid Feb - done with research into Slavic folk tales and moodboard creation;
- by Mid Feb - complete script written;
- by End of Feb/beginning of March - character designs are established; work on props, scenery and other parts needed to create animation;
- by 5th of March - storyboard and animatic done, await approval, small changes are still possible to make at this point (presentation);
- by end March - any animation tests are completed at this point (e.g. puppet tool, parallax effect for scenery); physical booklet/scroll showcasing development should be done at this point;
- by mid April - animation done;
- by 23.4. - animation completed to presentable level (presentation);
- by end April - any extra adjustments to the animation are done at this point, writing any extra blog posts;
- by 7.5.15. - everything is done and submitted on disk (module deadline).
Saturday, 24 January 2015
Time management|Extended Practice
This is the largest brief we had so far, worth 60 credits which translates into around 600 hours of work. Therefore good time management is crutial. Before starting I decided to create a simple breakdown of milestones I need to beat in order to get this module done.